When it comes to power, 'generous' isn't a number

A new warehouse or factory is no use without power, and the grid is at capacity. Here’s why supply is so hard to secure, what a megawatt actually runs and how to check what the site you’re evaluating has really got.

By Howard Cartwright, Group Project Director, Scarborough Group International

The marketing collateral for one new industrial and logistics scheme describes its power supply as “generous”. I’m sure it is. But you can’t size a chiller plant, a conveyor system or a row of lorry chargers on an adjective.

Most brochures for new industrial and logistics buildings are vague about power. Many give no figure at all, and very few put a date on a future upgrade.
A few years ago, nobody would have noticed.

Why the grid is full

Most factories and warehouses connect to the local distribution network, which is run by a regional operator, and not to the national transmission system. For years, a place in the queue for either was handed out on a first come, first served basis. Applying cost little, and a developer didn’t need to own the land or have planning permission to do it. So people applied, often several of them for the same opportunity, when only one could ever take it forward. Only about one application in ten goes ahead.

In April 2023 applying became more attractive still. Under changes made by Ofgem, a business connecting to the distribution network pays for the connection to its own site, and the cost of strengthening the wider network is shared among all customers. Requests grew quickly. Between November 2024 and June 2025 the demand holding connection offers tripled, from 41 gigawatts to 125, with proposed data centres accounting for at least 80. To put that in proportion, the whole country’s demand peaked at 51.5 gigawatts in 2025.

The national system had the same problem on a larger scale. By February 2025 its queue held 765 gigawatts of projects, mostly battery storage and solar schemes, and it has since been reordered by readiness and need.

The network operators have now tightened up as well. Since 2026, anyone applying for 5 MVA or more has had to show evidence of the land arrangements, a site plan and a realistic programme before they’re given a place. Ofgem has also consulted on a refundable fee to make the largest users commit.

Even with a tidier queue, the equipment has to be ordered and the network built. For a scheme of our size, a transformer takes 12 to 18 months to arrive, and cable rather less. On the largest national projects the International Energy Agency reports waits of up to four years.

What it’s costing

Nobody’s yet published a dependable figure for what the wait costs the businesses stuck in it.

The Government says projects have waited up to 15 years to connect and expects its reforms to release £40 billion a year of mainly private investment in energy alone. In a 2026 survey of 200 senior people in industry, a third of the firms that had experienced a grid delay said it had stopped their growth altogether, and a quarter of directors were considering building their next plant overseas. In west London, 3,900 homes with planning permission were left without a connection, with the upgrade they depend on not due until 2037. Fleet operators have been quoted dates as late as 2035, and as much as £5 million a site, to install chargers for electric lorries.

The sectors affected aren’t small ones. Logistics contributes £175 billion a year to the UK economy and employs 8% of the workforce. Manufacturing is worth £18.1 billion a year to Scotland and employs 178,000 people. The Forth Green Freeport, where our own site sits, is forecast to bring £7.9 billion of investment and up to 34,500 jobs over the next decade. All of those jobs need buildings, and all of those buildings need a supply.

Why buildings need more power than they used to

While the grid has been filling up, buildings have been asking more of it. When Tritax and Savills surveyed the sector in 2022, 7% of occupiers called power a barrier to securing space. In 2023 it was 11%, and in 2024 it was 36%. In the latest survey, 82% expect to need more power within three years. Savills finds that only 6.2% of the industrial and logistics buildings in its data have a supply of 3 MVA or more.

The reason is the same in every sector. Work that used to be done by hand, by diesel or by gas is increasingly being done by electricity.

In logistics, a modern distribution centre has little in common with the shed of ten years ago. Operators are using advanced automation to improve efficiency and accuracy and to make restocking easier. Pallet cranes work the high-bay racking. High-speed shuttles fetch goods from storage and bring them to the picker, who works hands-free. Tritax has suggested a fully automated warehouse might use five times the electricity of a traditional one for the same floor area. The same building increasingly has to charge the vans and lorries in the yard as well, and Savills calculates that charging 25 at a time needs at least 3 MVA.

In advanced manufacturing, the load is in the machines. Five-axis machining centres, laser cutters, robotic welding cells, injection moulding presses and the compressed air that feeds them all draw heavily, and they tend to draw at the same time. Clean rooms and close temperature control add a constant load on top.

In engineering and the energy supply chain, it’s heavy fabrication and testing, with large welding sets, overhead cranes, heat treatment and rigs that load a component thousands of times to prove it’ll last at sea.

In food and beverage, it’s refrigeration, which never switches off.

Across all of them, heat is moving from gas to electricity. Ovens, dryers, boilers and space heating that once ran on a gas main now need a place on the electrical supply. UK Energy Research Centre analysis finds that 65% of the industrial sites that are large sources of emissions would be short of electrical capacity by 2040.

All of this is manageable when the supply is there on the day you need it. Finding out that it isn’t, after you’ve signed a lease, is expensive.

It isn’t a matter of asking

There’s a common belief that a developer can simply order more power when an occupier turns up needing it. For a supply of any size, here’s roughly what it takes.

  • Show you control the land. For 5 MVA or more, the network operator now asks for evidence of the land arrangements, a site plan showing where the substations will go, and a programme that makes the requested date credible.
  • Wait for an offer. The operator has up to 65 working days to make one where extra-high-voltage works are involved.
  • Accept and pay. Offers are normally open for three months, and acceptance comes with a payment.
  • Agree who pays for what. The developer pays for the connection to its own site. Strengthening the wider network is a separate cost, and on our recent schemes the network operator has met the greater part of it. That isn’t automatic. It took up to two years of negotiation to settle, which is one reason so few sites secure power ahead of demand.
  • Keep to the milestones. Planning, land rights and a construction plan each have a deadline. Miss one and you get 60 days to put it right before the operator can move to end the agreement.
  • Agree the cable routes. Rights over land take from about five weeks on your own ground to as much as fifty where an overhead line crosses several owners.
  • Order the equipment. Then wait for it.
  • Pay to keep it. Once a supply is live, network operators charge daily for the capacity reserved, whether or not it’s being used.

It’s a long and potentially costly commitment, made well ahead of any rent. That’s why a figure and a date are worth asking for, and why so few brochures offer them.

What a megawatt runs

Power for a building is quoted in MVA, which for practical purposes you can read as megawatts. The table is a rough guide built from published case studies. Each row assumes the whole supply goes to that one use.

What a megawatt runs

Use 1 MVA 5 MVA 18 MVA
Conventional warehouse space About 600,000 sq ft About 3,000,000 sq ft About 10,800,000 sq ft
Electric lorries charging at the same time About 7 About 34 About 120
Electric lorry fleet supported 8 to 10 40 to 53 150 to 190

A rough guide built from published case studies. Each column assumes the whole supply goes to that one use, and is not a description of any particular site. Source: warehouse space from the BSRIA benchmark of 17 watts per square metre, before diversity; lorry charging from a published 5 MW installation serving 56 lorries, and from Savills.

Automation and production equipment vary so much from one system to the next that the only reliable figure is the one from your own supplier. Get it before you start looking at sites.

To get a rough figure for your own building, try the power tool below. Tell it what the building is for, how big it is and how many electric lorries will charge at the same time, and it will give you an illustrative range. It’s a starting point for a conversation with your engineers, not a substitute for one.

Four words to listen for

When a developer talks about power, one of four words will usually be in the sentence. They mean very different things.

  1. Applied. The developer has asked the network operator for a connection. It tells you nothing about how much they will get, or when.
  2. Offered. The network operator has quoted a capacity, a cost and a date. Offers lapse if they aren’t accepted.
  3. Secured. The offer has been accepted and paid for, and the capacity is reserved with a date attached. This is the first answer worth building a plan on.
  4. Energised. The supply is live. You could use it today.

Whichever word you hear, follow it with two questions. By when? And how much of it is mine?

Our own answers

It would be odd to write this and not give ours. At Queensferry One, 5 MVA is available now. A further 18 MVA is secured with Scottish Power and will be available in 2028, making 23 MVA in all.

Remember that only 6.2% of buildings have a supply of 3 MVA or more. The 5 MVA already on site is comfortably above that mark, and the 18 MVA to come is six times it.

It also arrives early. Queensferry One has a masterplan for more than 1.5 million sq ft, and it’ll be built out over many years. The power has been secured for all of it at the start. For the businesses that come first, that means far more capacity to draw on than a new building normally has, and room to add automation, charging or production later without going back to the queue.

None of this is an argument against any particular site. Plenty of them will have the power an occupier needs. But the only way to know is to ask for a figure and a date, and to be wary of anyone who offers an adjective instead.